Client

National Grid

Sector

Utilities

Value

£180,000

Completion Date

March 2012

Duration

11 weeks

Detail

Scope of Works

These works were a small part of a long term framework with National Grid covering the Midlands area. Works were undertaken at multiple Above Ground Installations (AGI’s). In the instance the pipework was surface blasted using Garnet followed by an application of protective coatings.

Challenges

Pipework was continually in use during our works leading to regular sudden changes in temperature to the work surfaces. Operatives needed to adapt to these changes in conditions to ensure sound adherence of the coatings.