Client
Coventry City Council
Sector
Highways
Value
£450,000
Completion Date
March 2011
Duration
32 weeks
Coventry Road
Scope of Works
ICS were contracted to undertake Scaffolding and Abrasive Blast cleaning and Coating of a large section of Coventry ring, works were undertaken over a two year program, with sections over live carriageways undertaken from Mobile Elevated working Platforms on Nights. All works were completed within program
Challenges
ICS were required to organise and manage night time road closures in order to undertake several sections of the work.